Brooks, OR
The Brooks OCDC project consisted of the exterior and interior renovations of an existing 34,880 sf, single story, Type 5-B construction, fully-sprinklered building. Interior work consisted of existing classrooms having child specific restrooms added, painting, flooring, acoustical wall coverings, new lockers, P-tac units installed for most classrooms, drinking fountains, ADA access upgrades, lighting upgrades and heating system upgrades. Exterior work consisted of repainting the exterior of the building and replacing exterior signage. Project duration was approximately 4 months and the cost was $1.4 million.
Project Details
OWNER
Oregon Child Development Coalition
ARCHITECT
Scott Edwards Architecture LLP
BUDGET
$1,740,207
PROJECT TYPE
COMPLETED
September 20, 2020